Abstract :
The study aimed at assessing the impact of Time and cost factors toward the completion of Mbeya city highway
road construction. Specifically, the study examined financial cost operational efficiency upon the whole process of supplying
materials in road construction, exploring the quality and technical performance of road construction project as well as
evaluating the time schedule of material supply for highway road construction. Where by a mixed approach was used on a
sample size of 100 respondents using contractors, consultants, and beneficiaries as target population, moreover, the
researcher used desk study and the questionnaire survey to get data about the impact of time and cost factors. Data was
analyzed using statistical package for social science (SPSS), Excel and Relative importance index (RII. The relative
importance index was useful for calculating the impact of time and cost factors by ranking different factors; ), The main
factor leading to delay upon the accomplishment of the road construction project in Mbeya was identified as inadequate
budget which ensure insufficient provision of fund upon project , and discussion was made in relation to other supporting
factors like poor project design, poor management process and political interference s. In the end of study recommendation
and conclusion was made following various policies reinforcement and relation upon different construction project of
Tanzania nation.
Keywords :
Road Construction Project, Time & Cost Factors and Road Project Accomplishment.
References :
- Awaad, S., Mansour, D. M., Mahdi, I., & Abdelrasheed, I. (2024). Impact of material supply chain on the productivity optimization for the construction of roads projects. Scientific Reports, 14(1), 3294.
- Badalpur, M., & Nurbakhsh, E. (2021). An application of WASPAS method in risk qualitative analysis: a case study of a road construction project in Iran. International Journal of Construction Management, 21(9), 910-918.
- Egina, J. C. (2021). Assessment of the Factors Causing Delay in Completion of Road Construction Projects in Tanzania: A Case of Tanzania National Roads Agency (Doctoral dissertation, The Open University of Tanzania).
- Hou, L., Fishman, T., Wang, R., Tzachor, A., Wang, H., Wang, P., ... & van der Voet, E. (2024). A comprehensive accounting of construction materials in belt and road initiative projects. Environmental Science & Technology, 58(35), 15575-15586.
- Kikwasi, G. J., & Escalante, C. (2018). Role of the construction sector and key bottlenecks to supply response in Tanzania (No. 2018/131). WIDER Working Paper.
- Kullaya, D. M., Alemu, M. K., & Yeom, C. H. (2022). An analysis of the main causes of delays in the completion of road construction projects: a case study of Tanzania. The Open Transportation Journal, 16(1).
- Kumar, M., & Kumari, S. (2025). Causes of delays in road construction projects: a systematic review. Journal of Financial Management of Property and Construction, 30(2), 256-294.
- Lyapin, A. A., Parinov, I. A., Buravchuk, N. I., Cherpakov, A. V., Shilyaeva, O. V., & Guryanova, O. V. (2020). Improving Road Pavement Characteristics. Springer, Cham. —2020.—254 p. DOI,
- Makovec, M. B. (2025). The Project Triangle Paradigm. Challenges of the Future/Izzivi Prihodnosti, 10(1). 10, 978-3.
- Mohajeri Borje Ghaleh, R., Pourrostam, T., Mansour Sharifloo, N., Majrouhi Sardroud, J., & Safa, E. (2021). Delays in the road construction projects from risk management perspective. Infrastructures, 6(9), 135.
- Muturi, W., & Oguya, S. A. (2016). Factors affecting performance of road construction projects in arid and semi-arid areas in Kenya. International journal of social science and information technology, 3(8), 908-929.
- Oluwajana, S. M., Ukoje, J. E., Okosun, S. E., & Aje, I. O. (2022). Factors affecting time and cost performance of road construction projects in Nigeria. African journal of applied research, 8(1), 72-84.
- Salaam, T. D. E. (2023). The Role of Monitoring and Evaluation on Performance of Road Construction Projects In Tanzania: A Case Of (Doctoral Dissertation, The Open University).
- Saki, R., & Yeom, C. (2022). Causes of variation orders in road construction projects in Tanzania. The Open Transportation Journal, 16(1).
- Simon, J. (2017). The Factors Causing Delays in Road Construction Projects in Tanzania: A of Case of TANROAD Dar es Salaam City (Doctoral dissertation, The Open University of Tanzania)
- Santoso, Djoen San, and Polwatta Gallage Madusha Piumal Gallage. "Critical factors affecting the performance of large construction projects in developing countries: A case study of Sri Lanka." Journal of Engineering, Design and Technology 18, no. 3 (2020): 531-556.
- Rivera, L., Baguec Jr, H., & Yeom, C. (2020). A study on causes of delay in road construction projects across 25 developing countries. Infrastructures, 5(10), 84.
- Tremblay, C. W. (2023). The Bermuda Triangle of the Iron Triangle: Three Angles, The Unholy Trinity, the Holy Grail, and the Triple Constraint (and a Tetrahedron). College and University, 98(3), 45-58.
- Truong, T. M. T., Friedrich, H., & Charoenngam, C. (2020). Success factors for financial sustainability of toll road projects: empirical evidence from China. Transportation Research Procedia, 48, 1848
- Zhao, F., Wu, H., Zhu, S., Zeng, H., Zhao, Z., Yang, X., & Zhang, S. (2023). Material stock analysis of urban road from nighttime light data based on a bottom-up approach. Environmental Research, 228, 115902.
- Zhasmukhambetova, A., Evdorides, H., & Davies, R. J. (2025). Critical Risk Factors Affecting Time and Cost in Highway Construction: A Global Systematic Literature Review. Future Transportation, 5(4), 192.
The study aimed at assessing the impact of Time and cost factors toward the completion of Mbeya city highway
road construction. Specifically, the study examined financial cost operational efficiency upon the whole process of supplying
materials in road construction, exploring the quality and technical performance of road construction project as well as
evaluating the time schedule of material supply for highway road construction. Where by a mixed approach was used on a
sample size of 100 respondents using contractors, consultants, and beneficiaries as target population, moreover, the
researcher used desk study and the questionnaire survey to get data about the impact of time and cost factors. Data was
analyzed using statistical package for social science (SPSS), Excel and Relative importance index (RII. The relative
importance index was useful for calculating the impact of time and cost factors by ranking different factors; ), The main
factor leading to delay upon the accomplishment of the road construction project in Mbeya was identified as inadequate
budget which ensure insufficient provision of fund upon project , and discussion was made in relation to other supporting
factors like poor project design, poor management process and political interference s. In the end of study recommendation
and conclusion was made following various policies reinforcement and relation upon different construction project of
Tanzania nation.
Keywords :
Road Construction Project, Time & Cost Factors and Road Project Accomplishment.