Reducing Material Overordering in UK Construction Projects: A NetLogo Study of Procurement Under Schedule Uncertainty


Authors : Prince Keshi

Volume/Issue : Volume 11 - 2026, Issue 11 - November


Google Scholar : https://tinyurl.com/5e2fbzpu

DOI : https://doi.org/10.38124/ijisrt/26nov1073

Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.


Abstract : Ordering more material than a job needs (material overordering) can protect installation work from shortages, but it can also leave costly stock at handover. This study examines how that trade-off changes when a construction buyer revises purchase orders against a shifting work schedule. A NetLogo 7.0.4 agent-based model represents a buyer, a supplier, two installation crews, 24 work packages and an order pipeline. A fully crossed BehaviorSpace experiment compares padded bulk buying, two standard rolling order rules and a rolling policy that caps its target at remaining demand.

Keywords : Construction Procurement; Material Overordering; Engineering Project Management; Schedule Uncertainty; AgentBased Modelling; Netlogo; Waste Prevention; SDG 12.

References :

  1. Ajayi, S. O., & Oyedele, L. O. (2018). Waste-efficient materials procurement for construction projects: A structural equation modelling of critical success factors. Waste Management, 75, 60–69. https://pubmed.ncbi.nlm.nih.gov/29426721/.
  2. Ajayi, S. O., Oyedele, L. O., Akinade, O. O., Bilal, M., Alaka, H. A., & Owolabi, H. A. (2017a). Optimising material procurement for construction waste minimization: An exploration of success factors. Sustainable Materials and Technologies, 11, 38–46. https://www.open-access.bcu.ac.uk/4462/.
  3. Ajayi, S. O., Oyedele, L. O., Bilal, M., Akinade, O. O., Alaka, H. A., & Owolabi, H. A. (2017b). Critical management practices influencing on-site waste minimization in construction projects. Waste Management, 59, 330–339. https://pureportal.bcu.ac.uk/en/publications/critical-management-practices-influencing-on-site-waste-minimizat/.
  4. Association for Project Management. (n.d.-a). What is project controls? https://www.apm.org.uk/resources/what-is-project-management/what-is-project-controls/.
  5. Association for Project Management. (n.d.-b). What is scheduling in project management? https://www.apm.org.uk/resources/what-is-project-management/what-is-scheduling-in-project-management/.
  6. Ballard, H. G. (2000). The Last Planner System of production control [Doctoral dissertation, University of Birmingham]. https://leanconstruction.org.uk/wp-content/uploads/2018/09/ballard2000-dissertation.pdf.
  7. Bonabeau, E. (2002). Agent-based modeling: Methods and techniques for simulating human systems. Proceedings of the National Academy of Sciences, 99(Suppl. 3), 7280–7287. https://pmc.ncbi.nlm.nih.gov/articles/PMC128598/.
  8. Cabinet Office. (2022). The Construction Playbook: Government guidance on sourcing and contracting public works projects and programmes (Version 1.1, September). https://www.gov.uk/government/publications/the-construction-playbook.
  9. Department for Environment, Food & Rural Affairs. (2011). Guidance on applying the waste hierarchy. https://www.gov.uk/government/publications/guidance-on-applying-the-waste-hierarchy.
  10. Department for Environment, Food & Rural Affairs. (2023). Waste prevention programme for England: Maximising Resources, Minimising Waste. https://www.gov.uk/government/publications/waste-prevention-programme-for-england-maximising-resources-minimising-waste.
  11. Department for Environment, Food & Rural Affairs. (2026). UK statistics on waste (23 September 2026 update). https://www.gov.uk/government/statistics/uk-waste-data/uk-statistics-on-waste.
  12. Donyavi, S., Flanagan, R., Assadi-Langroudi, A., & Parisi, L. (2024). Understanding the complexity of materials procurement in construction projects to build a conceptual framework influencing supply chain management of MSMEs. International Journal of Construction Management, 24(2), 177–186. https://www.tandfonline.com/doi/full/10.1080/15623599.2023.2267862.
  13. Grimm, V., Railsback, S. F., Vincenot, C. E., Berger, U., Gallagher, C., DeAngelis, D. L., Edmonds, B., Ge, J., Giske, J., Groeneveld, J., Johnston, A. S. A., Milles, A., Nabe-Nielsen, J., Polhill, J. G., Radchuk, V., Rohwäder, M.-S., Stillman, R. A., Thiele, J. C., & Ayllón, D. (2020). The ODD protocol for describing agent-based and other simulation models: A second update to improve clarity, replication, and structural realism. Journal of Artificial Societies and Social Simulation, 23(2), 7. https://pubs.usgs.gov/publication/70209554.
  14. Kahalimoghadam, M., & Thompson, R. G. (2026). Assessing the viability of construction and demolition waste recycling through agent-based modeling. International Journal of Construction Management. Advance online publication. https://www.tandfonline.com/doi/full/10.1080/15623599.2026.2653085.
  15. Keshi, P., Kundu, S., & Latif, M. (2025). Modelling human behaviour in COVID-19 vaccination centres: A discrete event simulation approach. International Journal of Innovative Science and Research Technology, 10(12), 203–213. https://doi.org/10.38124/ijisrt/25dec038.
  16. Knoeri, C., Nikolic, I., Althaus, H.-J., & Binder, C. R. (2014). Enhancing recycling of construction materials: An agent based model with empirically based decision parameters. Journal of Artificial Societies and Social Simulation, 17(3), 10. https://jasss.soc.surrey.ac.uk/17/3/10.html.
  17. Li, X., Li, J., Huang, Y., He, J., Liu, X., Dai, J., & Shen, Q. (2022). Construction enterprises’ adoption of green development behaviors: An agent-based modeling approach. Humanities and Social Sciences Communications, 9, Article 244. https://link.springer.com/article/10.1057/s41599-022-01263-9.
  18. Min, J. U., & Bjornsson, H. C. (2008). Agent-Based Construction Supply Chain Simulator (CS2) for measuring the value of real-time information sharing in construction. Journal of Management in Engineering, 24(4), 245–254. https://ascelibrary.org/doi/abs/10.1061/(ASCE)0742-597X(2008)24:4(245).
  19. NetLogo. (2026a). NetLogo download archive. Center for Connected Learning and Computer-Based Modeling. Retrieved 21 November 2026. https://www.netlogo.org/downloads/archive/.
  20. NetLogo. (2026b). BehaviorSpace. NetLogo 7.0.4 User Manual. https://docs.netlogo.org/7.0.4/behaviorspace.html.
  21. Osmani, M., Glass, J., & Price, A. D. F. (2008). Architects’ perspectives on construction waste reduction by design. Waste Management, 28(7), 1147–1158. https://pubmed.ncbi.nlm.nih.gov/17624757/.
  22. Sargent, R. G. (2013). Verification and validation of simulation models. Journal of Simulation, 7(1), 12–24. https://link.springer.com/article/10.1057/jos.2012.20.
  23. Tommelein, I. D., Riley, D. R., & Howell, G. A. (1999). Parade Game: Impact of work flow variability on trade performance. Journal of Construction Engineering and Management, 125(5), 304–310. https://pure.psu.edu/en/publications/parade-game-impact-of-work-flow-variability-on-trade-performance/.
  24. UK SDG Data. (n.d.). Goal 12: Responsible consumption and production. https://sdgdata.gov.uk/12/.
  25. United Nations Statistics Division. (n.d.). SDG indicators: Metadata repository, Goal 12. https://unstats.un.org/sdgs/metadata/.
  26. Vrijhoef, R., & Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management, 6(3–4), 169–178. https://repository.tno.nl/SingleDoc?docId=16260.
  27. Wilensky, U. (1999). NetLogo [Computer software]. Center for Connected Learning and Computer-Based Modeling, Northwestern University, Evanston, IL. https://docs.netlogo.org/copyright.

Ordering more material than a job needs (material overordering) can protect installation work from shortages, but it can also leave costly stock at handover. This study examines how that trade-off changes when a construction buyer revises purchase orders against a shifting work schedule. A NetLogo 7.0.4 agent-based model represents a buyer, a supplier, two installation crews, 24 work packages and an order pipeline. A fully crossed BehaviorSpace experiment compares padded bulk buying, two standard rolling order rules and a rolling policy that caps its target at remaining demand.

Keywords : Construction Procurement; Material Overordering; Engineering Project Management; Schedule Uncertainty; AgentBased Modelling; Netlogo; Waste Prevention; SDG 12.

Paper Submission Last Date
30 - November - 2026

SUBMIT YOUR PAPER CALL FOR PAPERS
Video Explanation for Published paper

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe