Abstract :
PT. Mega Bara Semesta is one of the
companies engaged in the field of coal mining business
services in Tanjung Agung, Muara Enim PT. Mega Bara
Semesta has the same production target every year with
an overburden production target of 166,000
BCM/month. The purpose of this study was to determine
the planned needs of the transportation equipment and
the factors that influence the productivity of the
transportation equipment to achieve the stripping target.
The productivity of the Caterpillar 340D2L excavator
loader is 224 BCM/hour. While the productivity of the
Scania P380 dumptruck is 28 BCM/hour. Calculation of
the number of transportation equipment needs that have
been planned based on the linear programming method
at the PT. Mega Bara Semesta said that the Scania P 380
dumptruck needed 16 units and the Caterpillar 340
excavator needed 2 units. Tool productivity is influenced
by the following factors, namely material factors, work
efficiency, and tool cycle time.
Keywords :
Overburden, Linear Programming, Productivity.
PT. Mega Bara Semesta is one of the
companies engaged in the field of coal mining business
services in Tanjung Agung, Muara Enim PT. Mega Bara
Semesta has the same production target every year with
an overburden production target of 166,000
BCM/month. The purpose of this study was to determine
the planned needs of the transportation equipment and
the factors that influence the productivity of the
transportation equipment to achieve the stripping target.
The productivity of the Caterpillar 340D2L excavator
loader is 224 BCM/hour. While the productivity of the
Scania P380 dumptruck is 28 BCM/hour. Calculation of
the number of transportation equipment needs that have
been planned based on the linear programming method
at the PT. Mega Bara Semesta said that the Scania P 380
dumptruck needed 16 units and the Caterpillar 340
excavator needed 2 units. Tool productivity is influenced
by the following factors, namely material factors, work
efficiency, and tool cycle time.
Keywords :
Overburden, Linear Programming, Productivity.