Authors :
Yeny Kumalaningrum; Irfan Prasetia
Volume/Issue :
Volume 9 - 2024, Issue 2 - February
Google Scholar :
http://tinyurl.com/57mtzk88
Scribd :
http://tinyurl.com/4w54r5p9
DOI :
https://doi.org/10.5281/zenodo.10686815
Abstract :
PKRTLH activities are carried out regularly
every year by the Katingan Regency Government to
overcome the high number of uninhabitable houses.The
implementation of PKRTLH activities is planned for 20
weeks with a fixed cost per housing unit of IDR
20,000,000. Based on the experience of previous years, it
is known that this activity often experiences delays from
the set schedule. Delays in one stage of the activity will
affect the next stage, so time control is needed with
monitoring activities. To be able to monitor PKRTLH
activities, time performance calculations can be made.
The purpose of this research is to obtain Estimated
Duration (ED) calculations using the Earned Value
Management (EVM) method and advanced methods,
namely Earned Schedule (ES) and Time Performance
Index (TPI). The data used comes from the progress
data of PKRTLH Activities2022, then the data is
analyzed by the above methods. The results of the
analysis, in the reference period in Week 11, show the
SPI value = 0.635, while the TPI value = 0.636.
Prediction results, the weight of the plan cumulative
progress in Week 11 can only be achieved in Week 17.
Seen from the calculation of ES and TPI, it is predicted
that the Total Time Estimate (T') of PKRTLH activities
will be delayed from the plan for 20 weeks to 31 weeks.
Keywords :
Project duration prediction; EVM; TPI. I. INTRODUCTION
PKRTLH activities are carried out regularly
every year by the Katingan Regency Government to
overcome the high number of uninhabitable houses.The
implementation of PKRTLH activities is planned for 20
weeks with a fixed cost per housing unit of IDR
20,000,000. Based on the experience of previous years, it
is known that this activity often experiences delays from
the set schedule. Delays in one stage of the activity will
affect the next stage, so time control is needed with
monitoring activities. To be able to monitor PKRTLH
activities, time performance calculations can be made.
The purpose of this research is to obtain Estimated
Duration (ED) calculations using the Earned Value
Management (EVM) method and advanced methods,
namely Earned Schedule (ES) and Time Performance
Index (TPI). The data used comes from the progress
data of PKRTLH Activities2022, then the data is
analyzed by the above methods. The results of the
analysis, in the reference period in Week 11, show the
SPI value = 0.635, while the TPI value = 0.636.
Prediction results, the weight of the plan cumulative
progress in Week 11 can only be achieved in Week 17.
Seen from the calculation of ES and TPI, it is predicted
that the Total Time Estimate (T') of PKRTLH activities
will be delayed from the plan for 20 weeks to 31 weeks.
Keywords :
Project duration prediction; EVM; TPI. I. INTRODUCTION