Authors :
Ndang Subianto; Mawardi Amin
Volume/Issue :
Volume 7 - 2022, Issue 6 - June
Google Scholar :
https://bit.ly/3IIfn9N
Scribd :
https://bit.ly/3ypygel
DOI :
https://doi.org/10.5281/zenodo.6812518
Abstract :
Risk factors in a dock construction work that
results in delays include labor, materials, equipment
and weather conditions which are factors studied in this
study. The purpose of this study is to analyze the risk of
delays that occur by identifying the dominant factor as
the cause of the delay that will occur and the
relationship between bound variables and free variables
and identifying work items that most affect
performance in the dock construction project. The data
analysis method used in this study is statistical analysis
using SPSS ver.26.0 and Relative Importance Index
(RII). Based on the results of the study, it was concluded
that the first factor that influenced the most dominant
cause of delay was the number of workers with a value
of 5.43, material quality and tool conditions with the
same value of 5.38. Secondly, the relationship between
the free variables to delays (bound variables) on the
dock construction project shows the result that the
correlation of labor, materials, tools is declared valid.
The third is the work that occupies the four highest
orders that have great potential in contributing delays,
namely mobilization and demobilization work with a
value of 0.990, erection of an inclined pile foundation
with a value of 0.981, erection of an upright pile
foundation with a value of 0.971 and splicing of piles
with a value of 0.952.
Keywords :
Dock project; risk identification; delay.
Risk factors in a dock construction work that
results in delays include labor, materials, equipment
and weather conditions which are factors studied in this
study. The purpose of this study is to analyze the risk of
delays that occur by identifying the dominant factor as
the cause of the delay that will occur and the
relationship between bound variables and free variables
and identifying work items that most affect
performance in the dock construction project. The data
analysis method used in this study is statistical analysis
using SPSS ver.26.0 and Relative Importance Index
(RII). Based on the results of the study, it was concluded
that the first factor that influenced the most dominant
cause of delay was the number of workers with a value
of 5.43, material quality and tool conditions with the
same value of 5.38. Secondly, the relationship between
the free variables to delays (bound variables) on the
dock construction project shows the result that the
correlation of labor, materials, tools is declared valid.
The third is the work that occupies the four highest
orders that have great potential in contributing delays,
namely mobilization and demobilization work with a
value of 0.990, erection of an inclined pile foundation
with a value of 0.981, erection of an upright pile
foundation with a value of 0.971 and splicing of piles
with a value of 0.952.
Keywords :
Dock project; risk identification; delay.