Saurav Rathor; Ajay Kumar Singh; Ayush Sangal
Volume/Issue :
Volume 9 - 2024, Issue 9 - September
Google Scholar :
https://tinyurl.com/59hv69pn
DOI :
https://doi.org/10.38124/ijisrt/24sep1544
Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.
Abstract :
The construction industry faces significant labor productivity challenges, impacting project timelines, costs, and
quality. This study investigates strategies and techniques to improve labor productivity in the construction industry,
focusing on technological advancements, workforce management, and process optimization. The construction business is
widely acknowledged as the largest and most challenging sector on a worldwide scale. Maximizing efficiency in this sector
is highly dependent on the strategic administration of personnel. Efficient deployment of human resources can greatly
enhance productivity growth. Construction projects primarily depend on human labor and the fundamental utilization of
handheld tools and equipment, with labor expenses constituting around 30% to 50% of the whole project expenditure. In
this study, the factors affecting the labour productivity in construction industry was analyzed. The study distribute 550
questionnaires to employees working in a construction company. Overall, 478 questionnaires were received and retained
for analysis. Findings reveals a complex interplay of internal, external, communication, resource, and miscellaneous
challenges that significantly influence project outcomes.
Keywords :
Labour Productivity, Construction, Human Resources, Internal Factors, External Factors.
References :
- Maloney, W. F. (1983). Productivity improvement: The influence of labor. Journal of Construction Engineering and Management, 109(3), 321–334. https://doi.org/10.1061/(ASCE)0733-9364(1983)109:3(321)
- Olomolaiye, P. O., Wahab, K., & Price, A. D. (1987). Problems influencing craftsmen’s productivity in Nigeria. Building and Environment, 22(4), 317–323. https://doi.org/10.1016/0360-1323(87)90024-2
- Horner, R., Talhouni, B., & Thomas, H. (1989). Preliminary results of major labour productivity monitoring pro- gramme. Proceedings of the 3rd Yugoslavian Symposium on Construction Management (pp. 18–28).
- Lim, E. C., & Alum, J. (1995). Construction productivity: Issues encountered by contractors in Singapore. International Journal of Project Management, 13(1), 51–58. https://doi.org/10.1016/0263-7863(95)95704-H
- Lim, E. C., & Alum, J. (1995). Construction productivity: Issues encountered by contractors in Singapore. International Journal of Project Management, 13(1), 51–58. https://doi.org/10.1016/0263-7863(95)95704-H
- Zakeri, M., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1996). A survey of constraints on Iranian construc- tion operatives’ productivity. Construction Management & Economics, 14(5), 417–426. https://doi.org/10.1080/014461996373287
- Zakeri, M., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1996). A survey of constraints on Iranian construc- tion operatives’ productivity. Construction Management & Economics, 14(5), 417–426. https://doi.org/10.1080/014461996373287
- Zakeri, M., Olomolaiye, P., Holt, G., & Harris, F. (1997). Factors affecting the motivation of Iranian con- struction operatives. Building and Environment, 32(2), 161–166. https://doi.org/10.1016/S0360-1323(96)00044-3
- Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing craftsmen’s productivity in Indonesia. International Journal of Project Management, 15(1), 21–30. https://doi.org/10.1016/S0263-7863(96)00019-1
- Zakeri, M., Olomolaiye, P., Holt, G., & Harris, F. (1997). Factors affecting the motivation of Iranian construction operatives. Building and Environment, 32(2), 161–166. https://doi.org/10.1016/S0360-1323(96)00044-3
- Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing craftsmen’s productivity in Indonesia. International Journal of Project Management, 15(1), 21–30. https://doi.org/10.1016/S0263-7863(96)00019-1
- Chitkara, K. (1998). Construction project management. Tata McGraw-Hill Education.
- Mustapha, F., &Naoum, S. (1998). Factors influencing the effectiveness of construction site managers.International Journal of Project Management, 16(1), 1–8. https://doi.org/10.1016/S0263-7863(97)00025-2
- Mustapha, F., &Naoum, S. (1998). Factors influencing the effectiveness of construction site managers. International Journal of Project Management, 16(1), 1–8. https://doi.org/10.1016/S0263-7863(97)00025-2
- Wilcox, S., Stringfellow, B., Harris, R., & Martin, B. (2000). Management and productivity. Transportation research board, committee on management and productivity.
- Arditi, D., &Mochtar, K. (2000). Trends in productivity improvement in the US construction industry. Construction Management & Economics, 18(1), 15–27. https://doi.org/10.1080/014461900370915
- Arditi, D., &Mochtar, K. (2000). Trends in productivity improvement in the US construction industry.Construction Management & Economics, 18(1), 15–27. https://doi.org/10.1080/014461900370915
- Mctague, B., &Jergeas, G. (2002). Productivity improvements on Alberta major construction projects: Phase I-Back to basics. Alberta economic development.
- Hanna, A. S., Peterson, P., & Lee, M.-J. (2002). Benchmarking productivity indicators for electrical/mechanical pro- jects. Journal of Construction Engineering and Management, 128(4), 331–337. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(331)
- Liberda, M., Ruwanpura, J., &Jergeas, G. (2003). Construction productivity improvement: A study of human, management and external issues. Construction Research Congress: Wind of Change: Integration and Innovation.
- Srinavin, K., & Mohamed, S. (2003). Thermal environment and construction workers’ productivity: Some evidence from Thailand. Building and Environment, 38(2), 339– 345. https://doi.org/10.1016/S0360-1323(02)00067-7
- Ng, S. T., Skitmore, R. M., Lam, K. C., & Poon, A. W. (2004). Demotivating factors influencing the productivity of civil engineering projects. International Journal of Project Management, 22(2), 139–146. https://doi.org/10.1016/S0263-7863(03)00061-9
- Tam, C., Zeng, S., & Deng, Z. (2004). Identifying elements of poor construction safety management in China. Safety Science, 42(7), 569–586. https://doi.org/10.1016/j.ssci.2003.09.001
- Kadir, M. A., Lee, W., Jaafar, M., Sapuan, S., & Ali, A. (2005). Factors affecting construction labourproduc- tivity for Malaysian residential projects. Structural survey.
- Coelli, T. J., Rao, D. S. P., O’donnell, C. J., &Battese, G. E. (2005). An introduction to efficiency and productivity analysis. Springer Science & Business Media.
The construction industry faces significant labor productivity challenges, impacting project timelines, costs, and
quality. This study investigates strategies and techniques to improve labor productivity in the construction industry,
focusing on technological advancements, workforce management, and process optimization. The construction business is
widely acknowledged as the largest and most challenging sector on a worldwide scale. Maximizing efficiency in this sector
is highly dependent on the strategic administration of personnel. Efficient deployment of human resources can greatly
enhance productivity growth. Construction projects primarily depend on human labor and the fundamental utilization of
handheld tools and equipment, with labor expenses constituting around 30% to 50% of the whole project expenditure. In
this study, the factors affecting the labour productivity in construction industry was analyzed. The study distribute 550
questionnaires to employees working in a construction company. Overall, 478 questionnaires were received and retained
for analysis. Findings reveals a complex interplay of internal, external, communication, resource, and miscellaneous
challenges that significantly influence project outcomes.
Keywords :
Labour Productivity, Construction, Human Resources, Internal Factors, External Factors.