Authors :
Niken Empina Putri; Erry Rimawan; Erik Odi Wijaya; Setiawan; Ojakma Sihar P.T
Volume/Issue :
Volume 5 - 2020, Issue 12 - December
Google Scholar :
http://bitly.ws/9nMw
Scribd :
https://bit.ly/38uQAWt
Abstract :
In a project that uses a lump sum as a
reference in submitting a bid is a design drawing so that
high accuracy is needed in reading the image and
calculating the Bill of Quantity (BOQ) and the Budget
Plan (RAB). With the THB contract, the owner and
contractor agree with their best efforts to review the
design including the selection of materials and
equipment in order to achieve the optimal contract
value. In this case, the risk that is experienced is that it
takes a long time to calculate progress so that it can
disrupt cash flow which results in delays in
implementation. The purpose of this study is to identify
and determine the factors that affect the project risk
from the unit price contract type, lump sum and
wholesale price target (THB). Determine the type of
contract that has the least risk in choosing the type of
contract. From the factor weights that have been
calculated using the Analytic Hierarchy Process (AHP)
method, it is explained that the lump sum contract type
is indeed relatively more risky to the ratio of profit to
risk in project implementation. Whereas the type of
contract with the least risk is the wholesale price target
with the score of each type of contract, the unit price is
in the second rank with a score of 0.423, lump sum is in
the third rank with a score of 0.418, and THB is in the
first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. From the factor weights that
have been calculated using the Analytic Hierarchy
Process (AHP) method, it is explained that the lump sum
contract type is indeed relatively more risky to the ratio
of profit to risk in project implementation. While the
type of contract with the least risk is the wholesale price
target with a score for each type of contract, the unit
price is in the second rank with a score of 0.423, lump
sum is in the third rank with a score of 0.418, and THB
is in the first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. From the factor weights that
have been calculated using the Analytic Hierarchy
Process (AHP) method, it is explained that the lump sum
contract type is indeed relatively more risky to the ratio
of profit to risk in project implementation. While the
type of contract with the least risk is the wholesale price
target with a score for each type of contract, the unit
price is in the second rank with a score of 0.423, lump
sum is in the third rank with a score of 0.418, and THB
is in the first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. While the type of contract with
the least risk is the wholesale price target with a score
for each type of contract, the unit price is in the second
rank with a score of 0.423, lump sum is in the third rank
with a score of 0.418, and THB is in the first position
with a score of 0.469. So that the implementation is more
efficient using the Contract Price Target (THB) type.
While the type of contract with the least risk is the
wholesale price target with a score for each type of
contract, the unit price is in the second rank with a score
of 0.423, lump sum is in the third rank with a score of
0.418, and THB is in the first position with a score of
0.469. So that the implementation is more efficient using
the Contract Price Target (THB) type
Keywords :
Lump Sum, Unit Price, THB, Risk, AHP.
In a project that uses a lump sum as a
reference in submitting a bid is a design drawing so that
high accuracy is needed in reading the image and
calculating the Bill of Quantity (BOQ) and the Budget
Plan (RAB). With the THB contract, the owner and
contractor agree with their best efforts to review the
design including the selection of materials and
equipment in order to achieve the optimal contract
value. In this case, the risk that is experienced is that it
takes a long time to calculate progress so that it can
disrupt cash flow which results in delays in
implementation. The purpose of this study is to identify
and determine the factors that affect the project risk
from the unit price contract type, lump sum and
wholesale price target (THB). Determine the type of
contract that has the least risk in choosing the type of
contract. From the factor weights that have been
calculated using the Analytic Hierarchy Process (AHP)
method, it is explained that the lump sum contract type
is indeed relatively more risky to the ratio of profit to
risk in project implementation. Whereas the type of
contract with the least risk is the wholesale price target
with the score of each type of contract, the unit price is
in the second rank with a score of 0.423, lump sum is in
the third rank with a score of 0.418, and THB is in the
first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. From the factor weights that
have been calculated using the Analytic Hierarchy
Process (AHP) method, it is explained that the lump sum
contract type is indeed relatively more risky to the ratio
of profit to risk in project implementation. While the
type of contract with the least risk is the wholesale price
target with a score for each type of contract, the unit
price is in the second rank with a score of 0.423, lump
sum is in the third rank with a score of 0.418, and THB
is in the first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. From the factor weights that
have been calculated using the Analytic Hierarchy
Process (AHP) method, it is explained that the lump sum
contract type is indeed relatively more risky to the ratio
of profit to risk in project implementation. While the
type of contract with the least risk is the wholesale price
target with a score for each type of contract, the unit
price is in the second rank with a score of 0.423, lump
sum is in the third rank with a score of 0.418, and THB
is in the first position with a score of 0.469. So that the
implementation is more efficient using the Contract
Price Target (THB) type. While the type of contract with
the least risk is the wholesale price target with a score
for each type of contract, the unit price is in the second
rank with a score of 0.423, lump sum is in the third rank
with a score of 0.418, and THB is in the first position
with a score of 0.469. So that the implementation is more
efficient using the Contract Price Target (THB) type.
While the type of contract with the least risk is the
wholesale price target with a score for each type of
contract, the unit price is in the second rank with a score
of 0.423, lump sum is in the third rank with a score of
0.418, and THB is in the first position with a score of
0.469. So that the implementation is more efficient using
the Contract Price Target (THB) type
Keywords :
Lump Sum, Unit Price, THB, Risk, AHP.