Abstract :
Variation order on the construction project
can negatively affect project implementation costs are
swelling. This occurs due to the factors that cause
variation work order. Data collection technique used
observation and interview methods and then be made a
factor analysis of causes and effects of variation order to
the cost of implementation. These results indicate that
the biggest factors causing variation work order is a
design change with a percentage of 60%, while the
smallest is the causative factor prime cost rate with the
percentage of 2% of the total number of jobs variation
order. The impact on costs due to the variation of work
orders amounted to 4.78% of the amount of the initial
contract with the percentage of 34.85% work structures
and architectural work for 65.15% of the total variation
work order.
Keywords :
Variation order, construction, contract, cost, etc.
Variation order on the construction project
can negatively affect project implementation costs are
swelling. This occurs due to the factors that cause
variation work order. Data collection technique used
observation and interview methods and then be made a
factor analysis of causes and effects of variation order to
the cost of implementation. These results indicate that
the biggest factors causing variation work order is a
design change with a percentage of 60%, while the
smallest is the causative factor prime cost rate with the
percentage of 2% of the total number of jobs variation
order. The impact on costs due to the variation of work
orders amounted to 4.78% of the amount of the initial
contract with the percentage of 34.85% work structures
and architectural work for 65.15% of the total variation
work order.