Abstract :
The goal of this study is to use the
Kaizen approach to create changes to the PT PLN
(Persero) ULP Cilegon electricity connection business
process. In the customer connection business process,
researchers employ primary data by speaking with the
appropriate officers directly and making on-the-ground
observations. The PDCA method was used to assess the
research findings. The fishbone and 5why approaches
were initially utilized by the researcher to identify the
fundamental reasons why clients weren't receiving same-
day service. Three initiatives were implemented to
address the root of the issue with same-day service
connection services: outreach to connection officers
regarding the target same-day service; adding location
coordinates to the connection application file; and
implementing simultaneous equipment titles to guarantee
that all vendors complete their equipment and work
equipment. The 5W1H technique is used to arrange these
three objectives in an action plan.
Keywords :
Kaizen, fishbone diagram, 5why, 5W1H, business process improvement, customer complaints.
The goal of this study is to use the
Kaizen approach to create changes to the PT PLN
(Persero) ULP Cilegon electricity connection business
process. In the customer connection business process,
researchers employ primary data by speaking with the
appropriate officers directly and making on-the-ground
observations. The PDCA method was used to assess the
research findings. The fishbone and 5why approaches
were initially utilized by the researcher to identify the
fundamental reasons why clients weren't receiving same-
day service. Three initiatives were implemented to
address the root of the issue with same-day service
connection services: outreach to connection officers
regarding the target same-day service; adding location
coordinates to the connection application file; and
implementing simultaneous equipment titles to guarantee
that all vendors complete their equipment and work
equipment. The 5W1H technique is used to arrange these
three objectives in an action plan.