Authors :
Memory Makwasa; Dr. Kelvin Chibomba
Volume/Issue :
Volume 10 - 2025, Issue 12 - December
Google Scholar :
https://tinyurl.com/48j5tah8
Scribd :
https://tinyurl.com/snhdjhs4
DOI :
https://doi.org/10.38124/ijisrt/25dec1653
Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.
Abstract :
Infrastructure development is a critical catalyst for economic growth in Sub-Saharan Africa. However, road
construction projects in Zambia frequently encounter delays and cost overruns attributed to suboptimal resource
management. This study evaluates the effectiveness of material management strategies implemented during the
construction of the Lusaka-Ndola Dual Carriageway. Utilizing a descriptive case study design, data was gathered from 79
stakeholders using structured questionnaires and interviews. The findings indicate that while 71% of the project team
recognizes a formal management framework, the practical application is hampered by technical skill gaps and inconsistent
monitoring. Specifically, only 51% of respondents viewed current strategies as "moderately effective." The study
concludes that the integration of Total Quality Management (TQM) and digital inventory tracking is essential for
improving project performance.
Keywords :
Material Management, Total Quality Management (TQM), Infrastructure Development, Zambia, Lusaka-Ndola Road, Construction Performance.
References :
- Akintoye, A., & MacLeod, M. (1997). Risk analysis and management in construction. International Journal of Project Management, 15(1), 31-38.
- Aminbakhsh, S., Sheikhi, A., & Abolhasani, M. (2021). Resource allocation in construction projects: A review. International Journal of Project Management, 39(6), 567-583. https://doi.org/10.1016/j.ijproman.2021.05.001.
- Atkinson, R. (1999). Project management: Cost, time, and quality, two best guesses and a phenomenon, it’s time to accept other success criteria. International Journal of Project Management, 17(6), 337-342. https://doi.org/10.1016/S0263-7863(98)00069-6.
- Aubry, M., Hobbs, B., & Thuillier, D. (2020). A new framework for project management tools and strategies. Project Management Journal, 51(2), 27-40. https://doi.org/10.1177/8756972819898945.
- Aven, T., & Renn, O. (2010). Risk Management and Governance: Concepts, Guidelines and Applications. Springer Science & Business Media.
- Baccarini, D. (2019). The project success criteria and the project management success. International Journal of Project Management, 17(3), 279-284. https://doi.org/10.1016/S0263- 7863(98)00025-3.
- Belout, A., & Gauvreau, C. (2023). Communication in project management: A critical factor for success. Journal of Construction Engineering and Management, 149(5), 04023018. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002539.
- Besteiro, D., López, J., & Pérez, E. (2015). The impact of project management on project success: A review of empirical evidence. Project Management Review, 44(2), 60-74. https://doi.org/10.1177/8756972815058329.
- Boikanyo, D. H. (2012). An Investigation into the Application of Total Quality Management (TQM) in the Road Construction Industry in South Africa (Doctoral dissertation, University of Johannesburg).
- Brown, M., & Green, J. (2021). Transformational leadership and its impact on project performance. Leadership & Organization Development Journal, 42(3), 415-430. https://doi.org/10.1108/LODJ-09-2020-0401.
- Chabota, M. (2010). The factors that influence the quality of road construction projects in Zambia: A case of Government funded projects (Doctoral dissertation).
- Cheung, S. O., Wong, K. Y., & Wu, A. W. (2013). Towards an organizational culture framework for construction. International Journal of Project Management, 29(1), 33-44.
- Chileshe, N., & Kikwasi, G. J. (2014). Risk assessment and management practices of construction professionals in Tanzania. Journal of Engineering, Design and Technology, 12(4), 505-533.
- Chileshe, N., & Kikwasi, G. (2016). Material management practices in developing countries: Evidence from Tanzania. Construction Management and Economics, 34(5), 379-394.
- Cooper, D. R., & Schindler, P. S. (2014). Business Research Methods (12th ed.). McGraw-Hill/Irwin.
- Covin, T. (2021). Project monitoring and control systems: A critical review. Project Management.
- Covin, T. (2021). Project monitoring and control systems: A critical review. Project Management
- Dam, P. (2010). Total Quality Management (TQM) in the construction industry (Doctoral dissertation).
- El-Sayegh, S. M. (2008). Risk assessment and management in the UAE construction industry. International Journal of Project Management, 26(4), 431-438.
- Evans, J. R., & Lindsay, W. M. (1996). The Management and Control of Quality. West Publishing Company.
- Fitz-enz, J. (1990). Human Value Management: The New Strategy for Realizing General ROI. Jossey-Bass.
- Hoonakkera, P., Carayon, P., & Lacker, T. (2010). Quality management and total quality management in the construction industry. Total Quality Management & Business Excellence, 21(9), 953-969.
- Kojo, A. (2014). Implementation of Total Quality Management in the Road Construction Industry in Ghana (Doctoral dissertation).
- Kombo, D. K., & Tromp, D. L. (2006). Proposal and Thesis Writing: An Introduction. Paulines Publications Africa.
- Kothari, C. R. (2019). Research Methodology: Methods and Techniques. New Age International.
- Ling, F. Y. Y., & Hoi, L. (2006). Risks faced by Singapore firms when undertaking construction projects in India. International Journal of Project Management, 24(2), 164-170.
- Lingard, H., & Rowlinson, S. (2005). Occupational Health and Safety in Construction Project Management. Routledge.
- Makwasa, M. (2025). Thesis: Analyzing the effectiveness of material management in construction projects. ICU.
- Matindo, J. (2015). Effectiveness of Material Management in the attainment of organizational goals: A case of construction companies in Zambia (Master's thesis).
- Mugenda, O. M., & Mugenda, A. G. (1999). Research Methods: Quantitative and Qualitative Approaches. Acts Press.
- Mugenda, A. G. (2003). Research Methods: Quantitative and Qualitative Approaches. African Centre for Technology Studies.
- Muya, M. (2006). The construction industry's contribution to Zambia's GDP (Unpublished research paper).
- Patel, K., & Vyas, C. M. (2011). Construction materials management on project sites. National Conference on Recent Trends in Engineering & Technology, 1-5.
- Price, A. (2002). Human Resource Management in a Business Context. Cengage Learning EMEA.
- Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (6th ed.). Project Management Institute.
- Raballand, G., & Whitworth, A. (2012). Improving road maintenance and management in Zambia. World Bank.
- Tah, J. H. M., & Carr, V. (2001). Knowledge-based approach to construction project risk management. Journal of Computing in Civil Engineering, 15(3), 170-177.
- Takewaki, I. (2013). Critical Excitation Methods in Earthquake Engineering. Butterworth-Heinemann.
- Turner, J. R. (1993). The Handbook of Project-Based Management. McGraw-Hill.
- Ubani, E. C., & Ononuju, C. N. (2013). A study of critical factors causing delays in public housing projects in Nigeria. International Journal of Engineering and Technology, 3(2), 146-161.
- Wong, A., & Kanji, G. K. (1998). Quality management in the construction industry. Total Quality Management, 9(4-5), 263-265.
- Xiao, Z., Darko, P., & Korankye, B. (2019). Motivational Packages and Its Effects on Employee’s Performance: A Case of Ghanaian Organizations.
- Yamane, T. (1967). Statistics: An Introductory Analysis (2nd ed.). Harper and Row.
- Zou, P. X., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601-614.
Infrastructure development is a critical catalyst for economic growth in Sub-Saharan Africa. However, road
construction projects in Zambia frequently encounter delays and cost overruns attributed to suboptimal resource
management. This study evaluates the effectiveness of material management strategies implemented during the
construction of the Lusaka-Ndola Dual Carriageway. Utilizing a descriptive case study design, data was gathered from 79
stakeholders using structured questionnaires and interviews. The findings indicate that while 71% of the project team
recognizes a formal management framework, the practical application is hampered by technical skill gaps and inconsistent
monitoring. Specifically, only 51% of respondents viewed current strategies as "moderately effective." The study
concludes that the integration of Total Quality Management (TQM) and digital inventory tracking is essential for
improving project performance.
Keywords :
Material Management, Total Quality Management (TQM), Infrastructure Development, Zambia, Lusaka-Ndola Road, Construction Performance.