Abstract :
One of the most important factors in a
construction project is labor wages. To find out labor
wages, a measurement of labor productivity is needed
which will later help contractors in improving project
planning, which is one of the steps in getting a cost
budget. Productivity can be used as a parameter in
determining activity duration, number of workers, and
costs. The main problem is analyzing or measuring the
value of productivity/hours/people for each type of work
in determining wages. The target of construction cost
analysis using SNI 2007 is recalculated into SNI 2008.
Based on the results of research on the Laboratory
building construction project Dinas PU Nagan Raya The
results obtained for bricklaying work according to the
2007 SNI planner's wages were not more efficient when
compared to the 2008 SNI contract with details of the
2007 SNI work unit price of Rp. 18,000,-/person/m2 and
according to SNI 2008 it is Rp. 15,000,-/person/m2, while
from the results of work productivity in the field Rp.
21,085,- /person/m2. If for brick wall plastering work, the
wage calculation according to the 2007 SNI planner is
IDR. 7,000/person/m2 is not more efficient when
compared to the 2008 SNI piece rate of Rp. 16,000,-
/person/m2, while productivity in the field is Rp. 11,820,-
/person/m2. For painting work according to the 2007 SNI
planner Rp. 3,500,- /person/m2, not more efficient
compared to the 2008 SNI wholesale rate of Rp. 3,000,-
/person/m2, from productivity results in the field Rp.
11,975,- /person/m2.
Keywords :
Worker Productivity; Brick; Wages; Dinas PU; Nagan Raya.
One of the most important factors in a
construction project is labor wages. To find out labor
wages, a measurement of labor productivity is needed
which will later help contractors in improving project
planning, which is one of the steps in getting a cost
budget. Productivity can be used as a parameter in
determining activity duration, number of workers, and
costs. The main problem is analyzing or measuring the
value of productivity/hours/people for each type of work
in determining wages. The target of construction cost
analysis using SNI 2007 is recalculated into SNI 2008.
Based on the results of research on the Laboratory
building construction project Dinas PU Nagan Raya The
results obtained for bricklaying work according to the
2007 SNI planner's wages were not more efficient when
compared to the 2008 SNI contract with details of the
2007 SNI work unit price of Rp. 18,000,-/person/m2 and
according to SNI 2008 it is Rp. 15,000,-/person/m2, while
from the results of work productivity in the field Rp.
21,085,- /person/m2. If for brick wall plastering work, the
wage calculation according to the 2007 SNI planner is
IDR. 7,000/person/m2 is not more efficient when
compared to the 2008 SNI piece rate of Rp. 16,000,-
/person/m2, while productivity in the field is Rp. 11,820,-
/person/m2. For painting work according to the 2007 SNI
planner Rp. 3,500,- /person/m2, not more efficient
compared to the 2008 SNI wholesale rate of Rp. 3,000,-
/person/m2, from productivity results in the field Rp.
11,975,- /person/m2.
Keywords :
Worker Productivity; Brick; Wages; Dinas PU; Nagan Raya.