Authors :
Herdikma Muhammad; Dewi Nusraningrum
Volume/Issue :
Volume 9 - 2024, Issue 8 - August
Google Scholar :
https://tinyurl.com/mrxhkd2h
Scribd :
https://tinyurl.com/mrrazxtw
DOI :
https://doi.org/10.38124/ijisrt/IJISRT24AUG1249
Abstract :
This research is designed to analyze the factors
causing delays in the verification project of Domestic
Component Level (TKDN) usage in goods and services
procurement in Cilacap and to provide improvement
suggestions to PT XYZ. According to data from PT XYZ,
the TKDN Verification project in Cilacap was only 72%
complete by the set deadline, with 28% of the contracts
completed outside the specified timeframe. The method
used in this study is DMAIC (Define, Measure, Analyze,
Improve, & Control), which involves analysis using
fishbone diagrams, 5 why analysis, Pareto charts, and the
5W+1H technique. The main factors causing delays are the
availability of documents, verifiers, technology systems,
external factors, process documentation, and internal
communication processes. Alternatives to resolve the
delays in the TKDN Verification Project in Cilacap include
adding manpower, a checklist for document requirements,
using the system, upgrading outdated laptops for each
personnel, and conducting regular coordination meetings
for each verification activity.
Keywords :
Component; Project Delays, TKDN Verification, DMAIC, Pareto Chart, Fishbone Diagram, 5W+1H.
References :
- Aulia, N. A., & Aspiranti, T. (2023). Analisis Pengendalian Proyek dengan Menggunakan Metode Critical Path Method (CPM) untuk Meminimumkan Waktu Pengerjaan Proyek. Bandung Conference Series: Business and Management, 3(1). https://doi.org/10.29313/bcsbm.v3i1.7184
- Fazis, M., & Tugiah, T. (2022). Perencanaan Proyek dan Penjadwalan Proyek. Jurnal Sosial Teknologi, 2(12). https://doi.org/10.59188/jurnalsostech.v2i12.517
- Habibi, I., Nugraha, F. Z., & Sutrisno, S. (2023). Penerapan Critical Path Method pada Penyelesaian Proyek Rehabilitasi Jalan Parigi Lama di Kabupaten Sumedang. Go-Integratif : Jurnal Teknik Sistem Dan Industri, 4(01). https://doi.org/10.35261/gijtsi.v4i01.8307
- Hasan Zakaria, A., Firdaus, F., Febriansyah Arifin, K., Munawar, sum, & Gunawan, A. (2023). Pengaruh Penerapan Kebijakan TKDN (Tingkat Komponen Dalam Negeri) Terhadap Daya Saing Produk Keramik. In Jurnal Ekobis Dewantara (Vol. 6, Issue 1).
- Heizer, J., Render, B., & Munson, C. (2017). Operation Management, Sustainbility and Supply Chaing Management (12th ed).
- Hijrah, H., & Maulidar, M. (2021). Analisis dan Perancangan Sistem Manajemen Inventaris Menggunakan Metode Fishbone. Jurnal Teknologi Dan Manajemen Informatika, 7(2). https://doi.org/10.26905/jtmi.v7i2.6501
- Holifahtus Sakdiyah, S., Eltivia, N., & Afandi, A. (2022). Root Cause Analysis Using Fishbone Diagram: Company Management Decision Making. Journal of Applied Business, Taxation and Economics Research, 1(6). https://doi.org/10.54408/jabter.v1i6.103
- Jefri Satdika. (2022). The Analisis Manajamen Kontruksi Proyek Pembangunan Gedung Puskesmas Kajeung Kecamatan Sungai Mas. Jurnal Ilmiah Teknik Unida, 3(1). https://doi.org/10.55616/jitu.v3i1.211
- Keputusan Menteri Perindustrian Republik Indonesia. (2023). Penunjukan Lembaga Verifikasi Independen Pelaksana Perhitungan dan Verifikasi Besaran Nilai Tingkat Komponen Dalam Negeri dan Nilai Bobot Manfaat Perusahaan.
- Khalimatul Inayah, S., & Firdauzi, B. (2023). Analisis Manajemen Risiko K3 Metode Dmaic Pada Pekerjaan Proyek XYZ di Kabupaten Karawang. 18(1), 59–67. https://doi.org/10.26623/teknika.v18i1.6134
- Kuswardana, A., Eka Mayangsari, N., & Natsir Amrullah, H. (2023). Analisis Penyebab Kecelakaan Kerja Menggunakan Metode RCA (Fishbone Diagram Method And 5-Why Analysis) di PT. PAL Indonesia.
- Maghfiro, Y., Damat, D., & Manshur, H. A. (2023). Pengendalian Kualitas Proses Pengolahan Teh Hitam Ortodox Menggunakan Metode DMAIC Di PT. Pagilaran. AGRISAINTIFIKA: Jurnal Ilmu-Ilmu Pertanian, 7(1). https://doi.org/10.32585/ags.v7i1.3635
- Monoarfa, M. I., Hariyanto, Y., & Rasyid, A. (2021). Analisis Penyebab Bottleneck pada Aliran Produksi Briquette Charcoal dengan Menggunakan Diagram Tulang Ikan. Jambura Industrial Review, 1(1).
- Nusraningrum, D., & Syaputra, Y. (2022). RAM Analysis at Gas Turbine Power Plant with Six Sigma Method. European Journal of Business and Management Research, 7(4), 356–361. https://doi.org/10.24018/ejbmr.2022.7.4.1609
- Peraturan Menteri Energi dan Sumber Daya Mineral Republik Indonesia. (2013). Penggunaan Produk Dalam Negeri Pada Kegiatan Usaha Hulu Minyak dan Gas Bumi.
- Peraturan Menteri Perindustrian Republik Indonesia. (2011). Ketentuan dan Tata Cara Perhitungan Tingkat Komponen Dalam Negeri.
- Purnama Nugraha, A., & Nofirman. (2021). Pemakaian Spare Part Bus Transjakarta Dengan Metode Diagram Pareto. JTTM : Jurnal Terapan Teknik Mesin, 2(1). https://doi.org/10.37373/jttm.v2i1.80
- Puspitasari, Y. I., Mangare, J. B., & Pratasis, P. A. K. (2020). Analisis Faktor-Faktor Keterlambatan Pada Proyek Perumahan Casa De Viola dan Alternatif Penyelesaiannya. Jurnal Sipil Statik, 8, 141–146.
- Putri, C. G., & Nusraningrum, D. (2022). Subcontractors Selection of Building Construction Project Using Analytical Hierarchy Process (AHP) and Technique for Others Reference by Similarity (TOPSIS) Methods. Jurnal Manajemen Teori Dan Terapan | Journal of Theory and Applied Management, 15(2). https://doi.org/10.20473/jmtt.v15i2.35915
- Sugiyono. (2017). Metode Penelitian Kuantitatif, Kualitatif, dan R&D (Alfabeta).
- Susanti, I. (2016). Evaluasi Kualitas Layanan Jasa Sertifikasi Tingkat Komponen Dalam Negeri (TKDN) Di PT. Sucofindo. Jurnal PASTI.
- Talenta .P, S., & Al-Faritsy, A. Z. (2022). Penggunaan Metode DMAIC dan Poka Yoke Dalam Meminimalkan Terjadinya Cacat Produk Manhole Cover. Jurnal DISPROTEK, 13(2). https://doi.org/10.34001/jdpt.v13i2.3067
- Zakky. (2018). Pengertian Manajemen Menurut Para Ahli Secara Umum. In Zona Referensi.
This research is designed to analyze the factors
causing delays in the verification project of Domestic
Component Level (TKDN) usage in goods and services
procurement in Cilacap and to provide improvement
suggestions to PT XYZ. According to data from PT XYZ,
the TKDN Verification project in Cilacap was only 72%
complete by the set deadline, with 28% of the contracts
completed outside the specified timeframe. The method
used in this study is DMAIC (Define, Measure, Analyze,
Improve, & Control), which involves analysis using
fishbone diagrams, 5 why analysis, Pareto charts, and the
5W+1H technique. The main factors causing delays are the
availability of documents, verifiers, technology systems,
external factors, process documentation, and internal
communication processes. Alternatives to resolve the
delays in the TKDN Verification Project in Cilacap include
adding manpower, a checklist for document requirements,
using the system, upgrading outdated laptops for each
personnel, and conducting regular coordination meetings
for each verification activity.
Keywords :
Component; Project Delays, TKDN Verification, DMAIC, Pareto Chart, Fishbone Diagram, 5W+1H.