Analysis of Project Delays in the Verification of Domestic Component Level Utilization in Goods and Services Procurement in Cilacap


Authors : Herdikma Muhammad; Dewi Nusraningrum

Volume/Issue : Volume 9 - 2024, Issue 8 - August

Google Scholar : https://tinyurl.com/mrxhkd2h

Scribd : https://tinyurl.com/mrrazxtw

DOI : https://doi.org/10.38124/ijisrt/IJISRT24AUG1249

Abstract : This research is designed to analyze the factors causing delays in the verification project of Domestic Component Level (TKDN) usage in goods and services procurement in Cilacap and to provide improvement suggestions to PT XYZ. According to data from PT XYZ, the TKDN Verification project in Cilacap was only 72% complete by the set deadline, with 28% of the contracts completed outside the specified timeframe. The method used in this study is DMAIC (Define, Measure, Analyze, Improve, & Control), which involves analysis using fishbone diagrams, 5 why analysis, Pareto charts, and the 5W+1H technique. The main factors causing delays are the availability of documents, verifiers, technology systems, external factors, process documentation, and internal communication processes. Alternatives to resolve the delays in the TKDN Verification Project in Cilacap include adding manpower, a checklist for document requirements, using the system, upgrading outdated laptops for each personnel, and conducting regular coordination meetings for each verification activity.

Keywords : Component; Project Delays, TKDN Verification, DMAIC, Pareto Chart, Fishbone Diagram, 5W+1H.

References :

  1. Aulia, N. A., & Aspiranti, T. (2023). Analisis Pengendalian Proyek dengan Menggunakan Metode Critical Path Method (CPM) untuk Meminimumkan Waktu Pengerjaan Proyek. Bandung Conference Series: Business and Management, 3(1). https://doi.org/10.29313/bcsbm.v3i1.7184
  2. Fazis, M., & Tugiah, T. (2022). Perencanaan Proyek dan Penjadwalan Proyek. Jurnal Sosial Teknologi, 2(12). https://doi.org/10.59188/jurnalsostech.v2i12.517
  3. Habibi, I., Nugraha, F. Z., & Sutrisno, S. (2023). Penerapan Critical Path Method pada Penyelesaian Proyek Rehabilitasi Jalan Parigi Lama di Kabupaten Sumedang. Go-Integratif : Jurnal Teknik Sistem Dan Industri, 4(01). https://doi.org/10.35261/gijtsi.v4i01.8307
  4. Hasan Zakaria, A., Firdaus, F., Febriansyah Arifin, K., Munawar, sum, & Gunawan, A. (2023). Pengaruh Penerapan Kebijakan TKDN (Tingkat Komponen Dalam Negeri) Terhadap Daya Saing Produk Keramik. In Jurnal Ekobis Dewantara (Vol. 6, Issue 1).
  5. Heizer, J., Render, B., & Munson, C. (2017). Operation Management, Sustainbility and Supply Chaing Management (12th ed).
  6. Hijrah, H., & Maulidar, M. (2021). Analisis dan Perancangan Sistem Manajemen Inventaris Menggunakan Metode Fishbone. Jurnal Teknologi Dan Manajemen Informatika, 7(2). https://doi.org/10.26905/jtmi.v7i2.6501
  7. Holifahtus Sakdiyah, S., Eltivia, N., & Afandi, A. (2022). Root Cause Analysis Using Fishbone Diagram: Company Management Decision Making. Journal of Applied Business, Taxation and Economics Research, 1(6). https://doi.org/10.54408/jabter.v1i6.103
  8. Jefri Satdika. (2022). The Analisis Manajamen Kontruksi Proyek Pembangunan Gedung Puskesmas Kajeung Kecamatan Sungai Mas. Jurnal Ilmiah Teknik Unida, 3(1). https://doi.org/10.55616/jitu.v3i1.211
  9. Keputusan Menteri Perindustrian Republik Indonesia. (2023). Penunjukan Lembaga Verifikasi Independen Pelaksana Perhitungan dan Verifikasi Besaran Nilai Tingkat Komponen Dalam Negeri dan Nilai Bobot Manfaat Perusahaan.
  10. Khalimatul Inayah, S., & Firdauzi, B. (2023). Analisis Manajemen Risiko K3 Metode Dmaic Pada Pekerjaan Proyek XYZ di Kabupaten Karawang. 18(1), 59–67. https://doi.org/10.26623/teknika.v18i1.6134
  11. Kuswardana, A., Eka Mayangsari, N., & Natsir Amrullah, H. (2023). Analisis Penyebab Kecelakaan Kerja Menggunakan Metode RCA (Fishbone Diagram Method And 5-Why Analysis) di PT. PAL Indonesia.
  12. Maghfiro, Y., Damat, D., & Manshur, H. A. (2023). Pengendalian Kualitas Proses Pengolahan Teh Hitam Ortodox Menggunakan Metode DMAIC Di PT. Pagilaran. AGRISAINTIFIKA: Jurnal Ilmu-Ilmu Pertanian, 7(1). https://doi.org/10.32585/ags.v7i1.3635
  13. Monoarfa, M. I., Hariyanto, Y., & Rasyid, A. (2021). Analisis Penyebab Bottleneck pada Aliran Produksi Briquette Charcoal dengan Menggunakan Diagram Tulang Ikan. Jambura Industrial Review, 1(1).
  14. Nusraningrum, D., & Syaputra, Y. (2022). RAM Analysis at Gas Turbine Power Plant with Six Sigma Method. European Journal of Business and Management Research, 7(4), 356–361. https://doi.org/10.24018/ejbmr.2022.7.4.1609
  15. Peraturan Menteri Energi dan Sumber Daya Mineral Republik Indonesia. (2013). Penggunaan Produk Dalam Negeri Pada Kegiatan Usaha Hulu Minyak dan Gas Bumi.
  16. Peraturan Menteri Perindustrian Republik Indonesia. (2011). Ketentuan dan Tata Cara Perhitungan Tingkat Komponen Dalam Negeri.
  17. Purnama Nugraha, A., & Nofirman. (2021). Pemakaian Spare Part Bus Transjakarta Dengan Metode Diagram Pareto. JTTM : Jurnal Terapan Teknik Mesin, 2(1). https://doi.org/10.37373/jttm.v2i1.80
  18. Puspitasari, Y. I., Mangare, J. B., & Pratasis, P. A. K. (2020). Analisis Faktor-Faktor Keterlambatan Pada Proyek Perumahan Casa De Viola dan Alternatif Penyelesaiannya. Jurnal Sipil Statik, 8, 141–146.
  19. Putri, C. G., & Nusraningrum, D. (2022). Subcontractors Selection of Building Construction Project Using Analytical Hierarchy Process (AHP) and Technique for Others Reference by Similarity (TOPSIS) Methods. Jurnal Manajemen Teori Dan Terapan | Journal of Theory and Applied Management, 15(2). https://doi.org/10.20473/jmtt.v15i2.35915
  20. Sugiyono. (2017). Metode Penelitian Kuantitatif, Kualitatif, dan R&D (Alfabeta).
  21. Susanti, I. (2016). Evaluasi Kualitas Layanan Jasa Sertifikasi Tingkat  Komponen Dalam Negeri (TKDN) Di PT. Sucofindo. Jurnal PASTI.
  22. Talenta .P, S., & Al-Faritsy, A. Z. (2022). Penggunaan Metode DMAIC dan Poka Yoke Dalam Meminimalkan Terjadinya Cacat Produk Manhole Cover. Jurnal DISPROTEK, 13(2). https://doi.org/10.34001/jdpt.v13i2.3067
  23. Zakky. (2018). Pengertian Manajemen Menurut Para Ahli Secara Umum. In Zona Referensi.

This research is designed to analyze the factors causing delays in the verification project of Domestic Component Level (TKDN) usage in goods and services procurement in Cilacap and to provide improvement suggestions to PT XYZ. According to data from PT XYZ, the TKDN Verification project in Cilacap was only 72% complete by the set deadline, with 28% of the contracts completed outside the specified timeframe. The method used in this study is DMAIC (Define, Measure, Analyze, Improve, & Control), which involves analysis using fishbone diagrams, 5 why analysis, Pareto charts, and the 5W+1H technique. The main factors causing delays are the availability of documents, verifiers, technology systems, external factors, process documentation, and internal communication processes. Alternatives to resolve the delays in the TKDN Verification Project in Cilacap include adding manpower, a checklist for document requirements, using the system, upgrading outdated laptops for each personnel, and conducting regular coordination meetings for each verification activity.

Keywords : Component; Project Delays, TKDN Verification, DMAIC, Pareto Chart, Fishbone Diagram, 5W+1H.

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe