Abstract :
In carrying out construction work in the field, changes often occur in order to adapt to the location of the project implementation.
The term change is better known as contract change order (CCO). However, it should be noted that CCO can be detrimental to a
construction project. The aim of this research is to find out the dominant factors that cause contract change orders (CCO), to know the
influence of contract change orders(CCO) on contractor performance and to know strategies for preventing contract change orders (CCO)
in the implementation of provincial road construction projects in Central Sulawesi. The 35 respondents in this study included work owners
within the scope of the Central Sulawesi Province Department of Highways and Spatial Planning, consultants and contractors. Data
collection techniques through questionnaire surveys, interviews and documentation. Data analysis uses descriptive statistics, RRI, and
multiple linear regression. From the results of the data analysis, it was found that there are 5 dominant factors that influence CCO, namely
CCO occurs due to design changes , CCO occurs due to differences between specifications, drawings and BOQ in planning , CCO occurs
due to design errors , CCO occurs due to a mismatch between technical specifications and requirements in field , and CCO occurs because
of the socio- cultural conditions of the community around the project. The CCO that hasthe greatest influence on contractor performance
is design problems.
Keywords :
Road Construction Project, Contract Change Order.
References :
- M. Masdéu, “RECONCEPTUALIZING THE DESIGN STUDIO IN ARCHITECTURAL EDUCATION: DISTANCE LEARNING AND BLENDED LEARNING AS TRANSFORMATION FACTORS,” 2017. [Online]. Available: www.archnet- ijar.net/--https://archnet.org/collections/34
- M. Riska Dirgantoro and S. Hardjomuljad, “How to cite: ANALYSIS OF THE EFFECT OF VARIATION ORDER ON WASTEWATER PROJECTS”, doi:10.36418/syntax-idea.v5i6.2331.
- Kathy. Schwalbe, Introduction to project management.
- S. S. Jasrotia, S. S. Rai, S. Rai, and S. Giri, “Stage-wise green supply chain management and environmental performance: Impact of blockchain technology,” International Journal of Information Management Data Insights, vol. 4, no. 2, Nov. 2024, doi: 10.1016/j.jjimei.2024.100241.
- S. Jordan and M. Messner, “The Use of Forecast Accuracy Indicators to Improve Planning Quality: Insights from a Case Study,” European Accounting Review, vol. 29, no. 2, pp. 337–359, Mar. 2020, doi: 10.1080/09638180.2019.1577150.
- J. R. Meijer, M. A. J. Huijbregts, K. C. G. J. Schotten, and A. M. Schipper, “Global patterns of current and future road infrastructure,” Environmental Research Letters, vol. 13, no. 6, Jun. 2018, doi: 10.1088/1748- 9326/aabd42.
- P. Aghamohammadi, “" Top Margi THEORETICAL ANALYSIS OF CONTRACT CHANGE IN CONSTRUCTION PROJECTS THEORETICAL ANALYSIS OF CONTRACT CHANGE IN CONSTRUCTION PROJECTS,” 2014.
- “PROCUREMENT GUIDELINES FOR PROJECT SUCCESS IN COST PLANNING OF CONSTRUCTION PROJECTS BY MOLUSIWA STEPHAN RAMABODU SUBMITTED IN ACCORDANCE WITH THE REQUIREMENTS FOR THE DEGREE PHILOSOPHIAE DOCTOR IN THE FACULTY OF NATURAL AND AGRICULTURAL SCIENCES DEPARTMENT OF QUANTITY SURVEYING AND CONSTRUCTION MANAGEMENT AT THE.”
- A. S. Hyder and D. Abraha, “Product and Skills Development in Small-and Medium-sized High-tech Firms through International Strategic Alliances.”
- “Guidelines for the Development of Process Specifications, Instructions, and Controls for the Fabrication of Fiber-Reinforced Polymer Composites,” 2003.
- A. Bratama, “INTERNATIONAL JOURNAL OF MULTI SCIENCE THE INFLUENCE OF THE WORKING ENVIRONMENT ON EMPLOYEE PERFORMANCE IN CLASS II PUBLIC INSTITUTIONS (LAPAS) BANGKO”.
- A. Alameri, A. S. A. M. Alhammadi, A. H. Memon, I. A. Rahman, N. Ain, and N. Nasaruddin, “Assessing the Risk Level of the Challenges Faced In Construction Projects,” 2021. [Online]. Available: www.etasr.com
- B. Erdogan, C. Anumba, D. Bouchlaghem, and Y. Nielsen, “Change management in construction: the current context,” 2005.
- J. N. Desai, J. Pitroda, P. Jaydev, and J. Bhavsar, “A REVIEW ON CHANGE ORDER AND ASSESSINGCAUSES AFFECTING CHANGE ORDER IN CONSTRUCTION JOURNAL OF INTERNATIONAL ACADEMIC RESEARCH FOR MULTIDISCIPLINARY Impact Factor A REVIEW ON CHANGE ORDER AND ASSESSINGCAUSES AFFECTING CHANGE ORDER IN CONSTRUCTION,” 2015. [Online]. Available: www.jiarm.com
- W. P. Wibowo, B. Witjaksana, and H. T. Tjendani, “ANALYSIS OF CONTRACT CHANGE ORDER (CCO) COSTS IN BUILDING CONSTRUCTION PROJECTS,” 2023. [Online]. Available: https://ajesh.ph/index.php/gp
- L. Hongyan, F. Jingchun, Z. Ke, C. Xu, and Y. Ruijia, “An empirical study on the formation mechanism of trust between the owner and the PMC contractor under the PMC model,” Ain Shams Engineering Journal, vol. 14, no. 5, May 2023, doi: 10.1016/j.asej.2022.101974.
- N. Korotkova, J. Lilliesköld, and E. Hetemi, “Pursuing openness in the digital age: Insights from client– contractor knowledge collaboration at the project front end,” International Journal of Project Management, vol. 42, no. 1, Jan. 2024, doi: 10.1016/j.ijproman.2024.102564.
In carrying out construction work in the field, changes often occur in order to adapt to the location of the project implementation.
The term change is better known as contract change order (CCO). However, it should be noted that CCO can be detrimental to a
construction project. The aim of this research is to find out the dominant factors that cause contract change orders (CCO), to know the
influence of contract change orders(CCO) on contractor performance and to know strategies for preventing contract change orders (CCO)
in the implementation of provincial road construction projects in Central Sulawesi. The 35 respondents in this study included work owners
within the scope of the Central Sulawesi Province Department of Highways and Spatial Planning, consultants and contractors. Data
collection techniques through questionnaire surveys, interviews and documentation. Data analysis uses descriptive statistics, RRI, and
multiple linear regression. From the results of the data analysis, it was found that there are 5 dominant factors that influence CCO, namely
CCO occurs due to design changes , CCO occurs due to differences between specifications, drawings and BOQ in planning , CCO occurs
due to design errors , CCO occurs due to a mismatch between technical specifications and requirements in field , and CCO occurs because
of the socio- cultural conditions of the community around the project. The CCO that hasthe greatest influence on contractor performance
is design problems.
Keywords :
Road Construction Project, Contract Change Order.