Authors :
Lailatul Mukarromah; Fahirah F.; Adnan Fadjar
Volume/Issue :
Volume 11 - 2026, Issue 11 - November
Google Scholar :
https://tinyurl.com/2s3hhmxd
DOI :
https://doi.org/10.38124/ijisrt/26nov655
Note : A published paper may take 4-5
working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and
ResearchGate.
Abstract :
This study examines the factors associated with implementation consistency and those potentially related to inconsistency in road construction projects in Palu City. Four groups of factors-technical, managerial, administrative/contractual, and external-were examined through two separate analytical models. A descriptive quantitative approach was applied to five road construction projects funded by the 2023 Regional Budget (APBD). Primary data were collected through questionnaires administered to 30 purposively selected respondents, comprising supervising consultants and relevant technical personnel from the Palu City Public Works Department.
Keywords :
Road Construction; Construction Management; Implementation Consistency; Managerial Factors; Potential Inconsistency.
References :
- A. P. C. Chan, D. Scott, and A. P. L. Chan, “Factors affecting the success of a construction project,” Journal of Construction Engineering and Management, vol. 130, no. 1, pp. 153–155, 2004, doi: 10.1061/(ASCE)0733-9364(2004)130:1(153).
- V. Sanvido, F. Grobler, K. Parfitt, M. Guvenis, and M. Coyle, “Critical success factors for construction projects,” Journal of Construction Engineering and Management, vol. 118, no. 1, pp. 94–111, 1992, doi: 10.1061/(ASCE)0733-9364(1992)118:1(94).
- D. K. H. Chua, Y. C. Kog, and P. K. Loh, “Critical success factors for different project objectives,” Journal of Construction Engineering and Management, vol. 125, no. 3, pp. 142–150, 1999, doi: 10.1061/(ASCE)0733-9364(1999)125:3(142).
- W. M. Chan and M. M. Kumaraswamy, “A comparative study of causes of time overruns in Hong Kong construction projects,” International Journal of Project Management, vol. 15, no. 1, pp. 55–63, 1997, doi: 10.1016/S0263-7863(96)00039-7.
- S. A. Assaf and S. Al-Hejji, “Causes of delay in large construction projects,” International Journal of Project Management, vol. 24, no. 4, pp. 349–357, 2006, doi: 10.1016/j.ijproman.2005.11.010.
- M. Sambasivan and Y. W. Soon, “Causes and effects of delays in Malaysian construction industry,” International Journal of Project Management, vol. 25, no. 5, pp. 517–526, 2007, doi: 10.1016/j.ijproman.2006.11.007.
- S. M. El-Sayegh, “Risk assessment and allocation in the UAE construction industry,” International Journal of Project Management, vol. 26, no. 4, pp. 431–438, 2008, doi: 10.1016/j.ijproman.2007.07.004.
- K. C. Iyer and K. N. Jha, “Factors affecting cost performance: evidence from Indian construction projects,” International Journal of Project Management, vol. 23, no. 4, pp. 283–295, 2005, doi: 10.1016/j.ijproman.2004.10.003.
- K. C. Iyer and K. N. Jha, “Critical factors affecting schedule performance: evidence from Indian construction projects,” Journal of Construction Engineering and Management, vol. 132, no. 8, pp. 871–881, 2006, doi: 10.1061/(ASCE)0733-9364(2006)132:8(871).
- H. Doloi, A. Sawhney, K. C. Iyer, and S. Rentala, “Analysing factors affecting delays in Indian construction projects,” International Journal of Project Management, vol. 30, no. 4, pp. 479–489, 2012, doi: 10.1016/j.ijproman.2011.10.004.
- S. Durdyev and M. R. Hosseini, “Causes of delays on construction projects: a comprehensive list,” International Journal of Managing Projects in Business, vol. 13, no. 1, pp. 20–46, 2020, doi: 10.1108/IJMPB-09-2018-0178.
- M. Nadeem, I. M. Jiskani, M. S. Urwat, S. Uddin, K. Akhtar, and N. H. Khokhar, “Analysing delay factors in construction projects using Z-number approach: insights from Pakistan,” Canadian Journal of Civil Engineering, vol. 50, no. 12, pp. 966–983, 2023, doi: 10.1139/cjce-2022-0310.
- R. K. Mavi and C. Standing, “Critical success factors of sustainable project management in construction: a fuzzy DEMATEL-ANP approach,” Journal of Cleaner Production, vol. 194, pp. 751–765, 2018.
- T. Williams, “Identifying success factors in construction projects: a case study,” Project Management Journal, vol. 47, no. 1, pp. 97–112, 2016, doi: 10.1002/pmj.21558.
- Y. C. Kog and P. K. Loh, “Critical success factors for different components of construction projects,” Journal of Construction Engineering and Management, vol. 138, no. 4, pp. 520–528, 2012, doi: 10.1061/(ASCE)CO.1943-7862.0000464.
- A. Assaf, M. Al-Khalil, and M. Al-Hazmi, “Causes of delay in large building construction projects,” Journal of Management in Engineering, vol. 11, no. 2, pp. 45–50, 1995, doi: 10.1061/(ASCE)0742-597X(1995)11:2(45).
This study examines the factors associated with implementation consistency and those potentially related to inconsistency in road construction projects in Palu City. Four groups of factors-technical, managerial, administrative/contractual, and external-were examined through two separate analytical models. A descriptive quantitative approach was applied to five road construction projects funded by the 2023 Regional Budget (APBD). Primary data were collected through questionnaires administered to 30 purposively selected respondents, comprising supervising consultants and relevant technical personnel from the Palu City Public Works Department.
Keywords :
Road Construction; Construction Management; Implementation Consistency; Managerial Factors; Potential Inconsistency.